Delays and costly design blight Heathrow expansion



It will surprise the majority of people that the most important port in the UK for the export and import of goods is Heathrow Airport. By trade value, Heathrow is gateway for a quarter of the nation’s goods trade, worth nearly £300 billion per annum. You would expect as a consequence, how an expanded airport might impact this trade to have featured highly in the economic analysis of what a third runway might mean for the nation. You would be wrong to have presumed so. Very wrong. It did not feature at all, as confirmed yesterday in the House of Commons Transport Committee Report on the Government’s draft policy for expanding Heathrow.
On September 2nd, the Transport Committee heard evidence from four economists who were questioned over a couple of hours. Not until the last question, Members asked fifty-five in total, was airfreight specifically mentioned. The guarded reply, by a Department of Transport’s representative, suggested airfreight was a complex issue, hard to model, difficult to obtain data for, to conceptualise, and measured benefits of adding a runway for the airfreight industry (thus the economy) absent from the cost-benefit analysis.
The long-runway proposal was advanced more than a decade ago at the time of the Airport Commission’s inquiry. It has received little challenge from officials
Missed also in this and other replies was an opportunity to correct a common fallacy, that cargo and passengers fly separately. From Heathrow this is rarely the case. Almost without exception, long-haul passenger flights from there carry cargo, and lots of it, hidden beneath passengers’ feet. ‘Belly-hold’ freight does not enjoy a free ride, contributing about 12%-15% of gross revenues for long-haul flights, thus extending the variety and scope of commercial airline operations to reach airports and nations otherwise unserved directly from the UK.
Having a similar, but again little appreciated, effect on airline economics are international ‘transit’ passengers changing ‘planes at the Heathrow hub. Connecting passengers, now declining in importance following the general squeeze on capacity, once accounted for a sizeable percentage of Heathrow’s total. Nevertheless, current numbers far exceed those at other UK airports and, by contributing to aircraft loadings and airline revenues, transiting passengers like belly-hold cargo increase the viability of services to destinations otherwise unsustainable by UK passenger demand alone.
Adding cargo and passengers-in-transit to those originating or destined for London, provides a business model that is a weave of interconnecting airline networks and material flows replete with synergistic effects. Such complex interrelationships, spreading and deepening UK trade, are too frequently overlooked. The economic case for expansion of Heathrow and its trade flows is subtle but powerful, ill-served by a failure to model it and provide a forecast of a third runway’s trade impact.
If the benefits of expansion are understated, on the reverse side of the ledger, estimated costs are generous, if not extraordinarily large. Infrastructure supplementing a new runway is a partial explanation. Yet, the really costly feature is the 3.5 km-long runway design, placed, for environmental reasons, despite technological advances shrinking noise contours, north west of the airport. Its length entails spanning the M25 motorway, one of Britain’s busiest, thus establishing a considerable engineering challenge.
The long-runway proposal was advanced more than a decade ago at the time of the Airport Commission’s inquiry. It has received little challenge from officials, despite a much shorter airport-promoted design receiving approval from Gordon Brown’s government in 2009. The current proposal was justified because it enabled all types of four-engined wide-bodied aircraft to depart carrying a full payload. However, airfield performance of modern jets is continually improving, and airlines increasingly are substituting fuel-efficient long-haul twinjets. The decade-old design length is increasingly questionable.
Eight years ago, to an earlier Transport Committee inquiry, I proposed a two-phase approach, the initial runway length stopping short of the M25. This proposal, now adopted by the Arora Group for a competing bid, has several benefits. Simplification of the initial construction task defers significant costs and allows earlier availability of extra capacity, bringing forward revenues for the airport and connectivity benefits for the UK. It also allows more time for planning and executing the difficult phase crossing the M25, thereby reducing risks of disrupting a critical part of the UK strategic road network.
Why is this approach not being considered? The answer might lie in the current regulatory framework under which the airport is deemed to have substantial market power. When setting future charges the Regulatory Asset Base (RAB) model allows for a reasonable return on capital assets. Economists have suggested this approach, with its near guaranteed return, encourages the regulatee to over-invest. Heathrow’s owners have little incentive to reduce costs.
Meanwhile, the Heathrow expansion odyssey lumbers on 30 plus years since a third runway was first endorsed by government established inquiry. Despite exhausting bureaucratic perambulations, the economic case for expansion remains ill-served by inadequate research, and the financial case by reluctance to challenge a costly design.